Norcross staff presented a $3,061,637 construction budget and four proposed contract awards for the Expanded Downtown Parking Project at the October 19 policy work session; the City Council has not yet approved them.
Why it matters
The work would rebuild the City Hall parking area into 75 spaces and add a brick plaza, landscaping, lighting and stormwater improvements, affecting downtown access during a phased construction period.
What to watch
The contracts and budget appropriation are scheduled for a November 2 council vote. If approved, the agenda estimates construction would start in January 2027 and take 9 to 12 months.
Sources and documents2 sources
See an error, or have an update on this project? Tell Urban Atlanta.